MACHINE SET-UP
NOTE: The FRESH CUP machine weighs approximately 35 LBS. Use CAUTION when
unpacking and lifting machine. LIFT MACHINE FROM MACHINE BOTTOM ONLY.
DO NOT MOVE MACHINE UNLESS THE HOT WATER TANK IS DRAINED AND
EMPTY.
1. Open and install the drip tray grill and place drip tray into waste bin.
2. Connect water fitting with strainer on the rear of machine next to the power switch.
Plumber's Installation
Instructions
1) Brewer must be installed to comply with all applicable federal, state and local
plumbing codes and ordinances.
2) Plumb brewer in to water supply using 1/4 inch copper tubing. Flush water line
before installing brewer to remove sediment. Brewer should be connected to
COLD WATER LINE for best operation.
3) Water pressure should be at least 20 lbs. For less than a 25 ft. run, use 1/4"
tubing and connect to 1/2" or larger water line. The inlet water fitting on the back
of the brewer is a
1/4" flare fitting. It may be necessary to remove the plumbing cover box on the
rear of brewer to access water connection point.
4) If installed with saddle valve, the valve should have a minimum of 1/8" porthole for
up to
25 ft. run, and 5/16" porthole for over 25 ft. runs.
5) Turn on water supply and check for leaks.
WARNING: - Read and follow installation instructions before
plugging or wiring in machine to electrical circuit. Warranty will
be void if machine is connected to any voltage other than that
specified on the serial tag.