Preparations
1.
Check that the switch (SF1) for F750 is in position
"
2.
Check that the filling valves (QM10) and (QM11)
in the heat pump are fully closed.
Caution
Check the miniature circuit-breaker (FA1) in
the heat pump. It may have tripped during
transportation.
Connecting to heating
medium system
1.
Connect SAM 40 according to the outline diagram
on page 10.
2.
Fill with water using the filler valve (QM11) in F750.
3.
Vent the heating medium system with the vent
valves (QM20) above SAM 40, and the vent valves
in F750 and fill if necessary using the filler valve
(QM11) in F750.
Start-up and inspection
Start-up
NOTE
There must be water in the climate system
before the switch in F750 is set to " ".
1.
Set switch (SF1) onSAM 40 in position "1".
2.
Set the heat pump's switch (SF1) to "".
3.
Follow the instructions in the start guide in the
heat pump display. If the start guide does not start
when you start the heat pump, start it manually in
menu 5.7.
Commissioning
The first time the heat pump is started a start guide is
started. The start guide instructions state what needs
to carried out at the first start together with a run
through of the heat pump’s basic settings.
The start guide ensures that the start-up is carried out
correctly and cannot be bypassed. The start guide can
be started later in menu 5.7.
This applies to a heat pump with approximately 4 kW
rated output.
For a 15 kW heat pump the corresponding flow is from
0.09 l/s (324 l/h) to 0.14 l/s (504 l/h).
Caution
As long as the start guide is active, no function
in the installation will start automatically.
The guide will appear at each installation re-
start until it is deselected on the last page.
SAM 40Chapter 6 | Commissioning and adjusting18
6 Commissioning and adjusting