Installation
3-2
Part 1032059B
E 2003 Nordson Corporation
Manual 41-DURABLUE-MA-02
Installation Tasks
The installation sequence is as follows:
1. Verify that the required installation conditions and utilities exist.
2. Unpack and inspect the melter.
3. Mount the melter on the parent machine or support structure.
4. Connecting the electrical service.
5. Connect hot melt hoses and guns.
6. Set up the melter to work with the manufacturing process.
7. Install optional equipment.
8. (If used) Connect a gun driver, pattern controller, or timer.
9. Flush the melter.
10. Adjust the pressure control valve.
Experience of Installation Personnel
The instructions provided in this section are intended to be used by
personnel who have experience in the following subjects:
S Hot melt application processes
S Industrial power and control wiring
S Industrial mechanical installation practices
S Basic process control and instrumentation