47
Fibre cable and draw rope provided
in sound condition and correctly
jointed where applicable.
Duct
DuctCable/BFT left in planned location.
Correct rope/cables/tubing installed
as per Developer ‘How to’ guide.
Correct type of duct provided
and used.
Duct laid in required position, at
correct depth and installed in the
correct position in the Joint Box.
Duct properly trimmed and keyed
when set in walls.
Duct separation distance
maintained, or exception agreement
obtained and documented.
Ducts laid at minimum depth
(350mm), or exceptions agreed
and documented. (To be viewed in
footway where possible, if not check
via Joint Box).
Joint Box constructed as planned,
positioned correctly and conforms to
drawings. Alternatives agreed and
documented.
Temporary duct seals tted to
agreed standard.
Ducts positioned correctly on
external walls and in line with the
cable entry point.
Item being audited Category
Yes No N/A
Checked and
Acceptable
Standard?
Comments
Duct
Duct
Duct
Duct
Duct
Duct
Duct
Duct
Duct
Quality control checklist