4.1.1 Optional VDI 6022 compliance
To ensure that the unit complies with VDI 6022 Part 1 regulations, the installer
must make sure by visual inspection that all parts are clean before installation.
According to VDI 6022 Part 4, this visual inspection may only be performed by at
least Category A qualied personnel.
4.2 Step 1. Positioning and leveling
Caution
Always place the unit level to prevent damage and to ensure correct
functioning.
Make sure the local facilities match the required facilities for the IntrCooll®. Refer
to Installation requirements.
Positioning and leveling
4.3
Step 2. Duct connection to the IntrCooll
The design of the IntrCooll® facilitates to connect the unit directly to the duct via
the duct connection unit. There are dierent ways to connect the IntrCooll® to the
roof opening:
Oxycom recommends to use a exible duct connector.