17 Installation Manual
Planning for Installation
Knockout Locations
There are multiple knockouts on the inverter and battery enclosure (as
shown with the red arrows.
1", 1.5", 1.75"
.5", .75", 1", 1.5" (four locations
underneath the inverter).
1.5" & 2" (four
locations, two on
each side of the
battery enclosure).
Required Tools
Below is a list of recommended tools you will need to install EverVolt:
PARTS NAME DESCRIPTION QTY.
Gloves Cotton glove with urethane coating 1 Pair
Automatic Screw-
driver (+)
Driver with torque setting 1
Wrench M6/M8/M12 1
Wire Cutters Standard wire cutters 1
Crimping Tool Used for making power cables 1
Socket Wrench Battery terminals are 10mm 1
Screwdriver Standard screwdriver 1
Allen Wrench
4mm Allen wrench needed for enclosure
1