Commissioning
Operating Manual PNOZ mo4p
20942-EN-08
| 18
6.3 Connection example
I0
I1
I2
I3
I4
I5
I6
I7
I8
I9
I10
I11
I12
I13
I14
I15
I16
I17
I18
I19
A1
A1
A2
A2
CI+
CI-
CO-
CO+
T0
T1
T2
T3
O0
O1
O2
O3
OA0
24V
24V
0V
0V
13
14
23
24
K3
K4
S1
K2
K1
S3
L+
L-
13
14
23
24
S2
PNOZ m1p
PNOZ mo4p
K1
K2
K4
K3
33
34
43
44
K6
K5
K5
K6
6.4 Download modified project to the PNOZmulti system
As soon as an additional expansion module has been connected to the system, the project
must be amended in the PNOZmulti Configurator and downloaded back into the base unit.
Proceed as described in the operating manual for the base unit.
NOTICE
For the commissioning and after every user program change, you must
check whether the safety devices are functioning correctly.