COMMISSIONING
6.1 Start Up and Shut Down the Energy Storage System
6.1.1 Start Up
Step 1: Turn on the circuit breaker
Step 2: Press and hold the main switch for 2-3s,until the display is on
6.1.2 Shut Down
Automatically shut down, when the solar light intensity is not strong enough during sunrise and sunset or the
output voltage of photovoltaic system is less than the minimum input power of inverter, inverter will shut
down automatically.
Shut down manually, disconnect AC side circuit breaker first, if multiple inverters are connected, disconnect
the minor circuit breaker prior to disconnection of main circuit breaker. Disconnect the DC switch after
inverter has reported grid connection lost alarm.
6.2 Introduction of Human-Computer Interface
System commissioning
After the wiring is completed, please refer to the inverter manual for system commission and operation.
Note: Turn on the circuit breaker and main switch when using battery.
Figure 6.3
Human-computer interface