Mounting and Commissioning 3
This chapter is intended for experienced commissioning staff. He must be familiar with the commissioning of
protection and control systems, the management of power systems and the safety rules and regulations. Hard-
ware adjustments to the power system data might be necessary. The primary tests require the protected object
(line, transformer, etc.) to carry load.
3.1 Mounting and Connections 302
3.2 Checking Connections 321
3.3 Commissioning 327
3.4 Final Preparation of the Device 348