Immediately perform an inspection after such faults.
9.2.3 First service after installation or repair
Check after approx. 500 operating hours, but after not more than one year:
Check When the
motor is
running
At stand‐
still
The electrical parameters are maintained. X
The permissible bearing temperatures are not exceeded. X
The smooth running characteristics and machine running noise have not
deteriorated.
X
The foundation has no cracks or indentations. (*) X X
(*) You can perform these checks while the motor is at standstill or, if required, while running.
Further checks may be required if so specified in operating instructions of components
(Page 105) or in accordance with the plant-specific conditions.
If you find any deviations during the inspection, you must rectify them immediately. They
may otherwise damage the motor.