Commissioning
4.3 Connecting the inverter to the fieldbus
CU230P-2 Control Units
Compact Operating Instructions, 01/2017, A5E38815802B AA
41
Smoothed current actual
value
Control word according to
the VIK
Smoothed actual speed value
Control word 1 (STW1), PZD receive word 1 (word: r2050[0], bits: r2090.00 … r2090.15)
0 0 = OFF1 The motor brakes with the ramp-down time p1121 of the ramp-function generator. The
inverter switches off the motor at standstill.
0 → 1 = ON The inverter goes into the "ready" state. If, in addition bit 3 = 1, then the inverter
switches on the motor.
1
Switch off the motor immediately, the motor then coasts down to a standstill.
Precondition in order to be able to switch on the motor using bit 0 (ON command).
The motor brakes with the OFF3 ramp-down time p1135 down to standstill.
Precondition in order to be able to switch on the motor using bit 0 (ON command).
Switch off the motor immediately → motor coasts down to a standstill.
Precondition in order to be able to switch on the motor using bit 0 (ON command).
The inverter immediately sets its ramp-function generator output to 0.
The ramp-function generator can be enabled.
The output of the ramp-function generator stops at the actual value.
The output of the ramp-function generator follows the setpoint.
6 0 = Inhibit setpoint The inverter brakes the motor with the ramp-down time p1121 of the ramp-function
Motor accelerates with the ramp-up time p1120 to the setpoint.
7 0 → 1 = Acknowledge faults Acknowledge fault. If the ON command is still active (bit 0 = 1), the inverter switches to
The inverter ignores the process data from the fieldbus.
Control via fieldbus, the inverter accepts the process data from the fieldbus.
11 1 = Direction reversal Invert setpoint in the inverter.
13 1 = MOP up Increase the setpoint saved in the motorized potentiometer.
Reduce the setpoint saved in the motorized potentiometer.
Changes over between settings for different operation interfaces (command data sets).