Commissioning
4.3 Connecting the inverter to the fieldbus
CU230P-2 Control Units
Compact Operating Instructions, 01/2017, A5E38815802B AA
45
.01 p0844 BV27 No OFF2 Precondition in order to be able to switch on
the motor (ON command).
.02 p0848 BV28 No quick stop
.03 p0852 BV26 Enable operation
.04 p1140 BV26 Do not disable
The ramp-function generator can be enabled
.05 p1141 BV26 Enable RFG The output of the ramp-function generator
.06 p1142 BV26 Enable setpoint Motor accelerates with the ramp-up time p1120
.07 p2103 BV22 Acknowledge
--- N/A Reserved
.10 p0854 BV93 Master control by
Control via fieldbus, the inverter accepts the
process data from the fieldbus
Invert setpoint in the inverter
.13 p1035 N/A MOP raise Increase the setpoint saved in the motorized
.14 p1036 N/A MOP lower Reduce the setpoint saved in the motorized