TRANSPORTING AND LIFTING THE MACHINE
GTZZ14EJ&16EJ Operation Manual 8-3 © Dec 2021
TRANSPORTING THE
MACHINE
Follow these requirements when transporting the
machine by truck or trailer:
1. Before transport, turn the key switch on ground
controller to OFF, and remove the key.
2. Perform a thorough inspection of the machine to
prevent loose or untightened components.
3. Ensure the rope or belt is of sufficient capacity.
4. Use at least 4 ropes/belts to fasten the chassis and
one rope/belt for the platform.
5. Adjust the rigging to prevent damage to the rope/
belt.
6. To protect the boom components and platform load
sensors, do not apply too large a downward force to
the rope/belt fastened near the platform. It is
recommended to add a foam layer beneath the
platform and ensure the platform is suspended in
the air.
Figure 8-3