7 Commissioning SMA Solar Technology AG
28 FSS-IS-en-42 Installation Manual - Quick Reference Guide
Forecast-based battery charging:
Figure7: User interface of Sunny Portal with Forecast-based battery charging checkbox.
When commissioning the SMA Flexible Storage System, you can activate the Forecast-based battery charging
checkbox in the user interface of Sunny Portal (information on forecast-based charging see Planning Guidelines
"SMA Smart Home").
Requirements:
The SMA Flexible Storage System must be installed in accordance with the circuitry overviews.
The Sunny Home Manager, the Sunny Island and all other Speedwire devices must be connected to the same router.
The basic configuration of the Sunny Island inverter must have been performed (see Section 7.1).
DHCP must be enabled for the router of the system.
The router of the system must have an Internet connection.
Customer data E-mail address
Password for Sunny Portal access
Address of the PV system
Electricity tariff data
Electricity price for purchased electricity
Tariff times, if applicable (e.g., for tariffs with peak and off-peak tariff)
Feed-in tariff
Self-consumption tariff, if applicable
Device / customer data Required data and explanation