7 Commissioning SMA Solar Technology AG
28 FSS-IS-en-42 Installation Manual - Quick Reference Guide
Forecast-based battery charging:
Figure7: User interface of Sunny Portal with Forecast-based battery charging checkbox.
When commissioning the SMA Flexible Storage System, you can activate the Forecast-based battery charging
checkbox in the user interface of Sunny Portal (information on forecast-based charging see Planning Guidelines
"SMA Smart Home").
Requirements:
☐ The SMA Flexible Storage System must be installed in accordance with the circuitry overviews.
☐ The Sunny Home Manager, the Sunny Island and all other Speedwire devices must be connected to the same router.
☐ The basic configuration of the Sunny Island inverter must have been performed (see Section 7.1).
☐ DHCP must be enabled for the router of the system.
☐ The router of the system must have an Internet connection.
Customer data • E-mail address
• Password for Sunny Portal access
• Address of the PV system
• Electricity tariff data
– Electricity price for purchased electricity
– Tariff times, if applicable (e.g., for tariffs with peak and off-peak tariff)
– Feed-in tariff
– Self-consumption tariff, if applicable
Device / customer data Required data and explanation