8 Commissioning
SMA Solar Technology AG
Operating ManualHS-BM-3.28-10-BE-en-1044
8 Commissioning
8.1 Commissioning Procedure
This section describes the procedure for commissioning the SMA Home Storage.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure See
1. Check that all installed components have been cor-
rectly mounted and connected.
Section8.2, page44
2. If there is an SMA Home Manager installed, com-
mission the SMA Home Manager.
Manual for the SMA Data Manager
3. Start the commissioning of the battery modules. Section8.4, page46
4. Commission the inverter. Manual of the inverter
5. Establish a connection to the user interface of the
inverter.
Manual of the inverter
6. Log into the user interface and configure the sys-
tem.
Manual of the inverter
Check the configuration of the battery modules. Section8.5, page47
8.2 Checking the Mounting and Connection Work
Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for
the check is DINVDE0100-600.
Prerequisite:
Make sure that all batteries were correctly mounted and connected.
Procedure:
1. Measure the ground resistance and continuity of the grounding conductor.
2. Measure the insulation resistance.
3. Check the polarity between the inverter and battery.