8 Commissioning
SMA Solar Technology AG
Operating ManualHS-BM-3.28-10-BE-en-1046
E Current power and cur-
rent consumption
Shows the temporal progression of the PV power and the power consump-
tion of the household over the selected time period, for example.
F Status display The various areas display information on the current status of the system
such as:
Device status and system overview
Yield
Nominal energy throughput of the battery
Energy exchange at the grid-connection point
8.4 Commissioning the battery modules
Requirements:
The battery modules must be correctly mounted.
All cables must be correctly connected.
Procedure:
1. Open the cover of the DC switch on each battery module. The side cover must not be mounted for this.
2. Turn on the DC switches one after the other.
The green LED is glowing or flashing.
The blue LED is flashing first and starts glowing once a connection has been successfully established.
3. Close the cover of the DC switch on each battery module.
4. Attach the side covers.
5. Commission the inverter.
Also see:
LED signals of the battery modules⇒page19
Checking the configuration of the battery modules in the installation assistant⇒page47

Table of Contents

Other manuals for SMA Home Storage HS-BM-3.28-10