EasyManua.ls Logo

SMA SUNNY ISLAND 6.0H - Setting the Parameters

SMA SUNNY ISLAND 6.0H
36 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
5 Commissioning
SMA Solar Technology AG
System DescriptionSI44M-80H-13-MC-IA-en-1030
Log in as Installer.
Set the parameter Activation of communication test between the clusters to Off.
5.3 Commissioning an Off-Grid System
5.3.1 Commissioning the Multifunction Relays
In multicluster systems with MC-BOX-12.3-20, multifunction relays 1 and 2 in the master of the maincluster and
multifunction relay 2 in slave 1 of the maincluster are set permanently. Therefore, optional components and functions
can only be controlled via SunnyIsland inverters in the extensionclusters.
Set the functions of the multifunction relays in the SunnyIsland inverters of the extensionclusters (see operating
manual of the SunnyIsland inverter).
5.3.2 Testing the Load Shedding
Requirements:
The additional load-shedding contactor is connected to a multifunction relay in the master of the extensioncluster.
The battery inverter must be in operation (for information on starting the operation see the operating manual of the
inverter).
Procedure:
1. Activate the user interface of the inverter (see the inverter operating manual).
2. Log in as Installer.
3. Select the parameter Device > Multifunction relay > Operating mode > Operating mode of multifunction
relay.
4. Note the parameter value of the load-shedding contactor.
5. Set the parameter of the load-shedding contactor to Off.
6. If the load-shedding contactor does not discard the loads, carry out the following steps:
Check the configuration and eliminate the fault.
Ensure that the multifunction relay is correctly wired.
7. Set the load-shedding contactor parameter to the setting that has been noted down.
5.4 Commissioning a System With Increased Self-Consumption and
Battery-Backup Function
5.4.1 Adjusting the Configuration of the SunnyIsland
If multicluster systems are used with the Grid-Connect-Box for increased self-consumption and as a battery-backup
system, the following must be taken into account: Multicluster systems with Grid-Connect-Box may not be connected to
utility grids that require compliance with the European gird connection conditions in accordance with Regulation (EU)
2016/631 establishing a network code (also known as RfG).
Procedure:
1. For the planned installation site, check whether parameters of the PV inverter for grid monitoring of the
SunnyIsland must be set and adjusted.
2. Check the settings with your grid operator.
3. Access the SunnyIsland user interface (see user manual of the SunnyIsland).
4. Log in as Installer.

Table of Contents

Other manuals for SMA SUNNY ISLAND 6.0H

Related product manuals