10 Operation SMA Solar Technology America LLC
90 SI4548-6048-US-BE-en-21 Operating Manual
The Sunny Island also shows the following values one after the other in the upper line of the "Home
Screen" (parameter name and parameter value in 3-second intervals):
Bar display for output power or charging power (the direction of energy flow is displayed by
the arrows in the lower line)
Total active power of the inverter (cluster)
Active power of external source (total of all phases)
Present state of charge of the battery (SOC)
Meters (always one of five possibilities, depending on priority)
Remaining absorption time
Remaining generator warm-up time
Remaining Run1h time for the generator
Remaining time of Timer 1
Remaining time of Timer 2
Active charging process
Meaning of the Symbols that appear in the "Home Screen":
GRelay 2 status
H Warning message (exclamation mark)
Situational displaying of text and values
The display shows only values that are relevant in the actual system status. If there is no
generator connected, no generator values are displayed
Messages on the slave devices
On the slave devices, the upper line of the display shows the bar graph for output power or
charging power. The lower line of the display shows the device assignment (e.g. S1 for slave
1) and, where applicable, the status of external sources (*, for a description, see further above)
and the status of relays.
Symbol Meaning
Nominal power
Nominal load exceeded.
Direction of energy flow between grid/generator side, battery and load side.
Generation side (Generator/Grid) is on.