Electrical Connection SMA Solar Technology AG
22 WB33_38-IEN101830 Installation Guide
5.3 Connection to the Public Grid (AC)
Cable Sizing
The cable cross-section should be dimensioned so output losses do not exceed 1% at nominal power.
Maximum cable lengths relative to the cable cross-section are shown in the following table:
The conductor cross-sectional area required in individual cases depends on the following factors,
among others:
Ambient temperature,
•Routing method,
•UV resistance,
•Conduction losses,
Valid installation guidelines of the respective country (of the installation location).
Cable Requirements
Connection requirements of the utility operator
Always observe the connection requirements of the utility operator.
Cable cross-section Maximum cable length
WB 3300 WB 3800
4 mm² 18.5 m 16 m
Object Description Value
A External diameter 6 mm … 14 mm
B Conductor cross-section 4 mm²
C Strip insulation 8 mm