Commissioning SMA Solar Technology AG
36 WB33_38-IEN101830 Installation Guide
6 Commissioning
6.1 Commissioning the Inverter
1. Check the following requirements before commissioning:
– Correct mounting and correct connection of the inverter.
– Correct layout of the line circuit breaker.
– Correct grounding of the small wind turbine system in accordance with the instructions of the
manufacturer.
– The rectifier and overvoltage protection (e.g. WindyBoyProtectionBox) are installed
between the small wind turbine system and the inverter.
– Unnecessary DC inputs are closed with the corresponding DC connectors and sealing plugs.
2. Switch on the line circuit breaker.
3. Commission the small wind turbine system in accordance with the instructions of the
manufacturer.
☑ If green LED glows: commissioning has been successful.
or
☑ If green LED flashes: network connection conditions have not yet been reached. Wait until
the green LED lights up.
or
☑ The red or yellow LED is glowing or flashing: there is an error. Proceed to step 3.
4. Read section 9”Troubleshooting” (page51) and if necessary eliminate the fault or disturbance.
Self test in accordance with DK 5940, Ed. 2.2 for initial commissioning
(appliestoItaly only)
The Italian DK 5940 standard prescribes that an inverter can only operate on the public
grid after the disconnection times for overvoltage, undervoltage, minimum frequency and
maximum frequency have been checked.
Start the self-test as described in the section 6.2”Self-Test in accordance with DK 5940,
Ed. 2.2 (Applies to Italy Only)” (page37). The test takes approx. 8minutes.
Object Description
A Green LED: Operation
B Red LED: Ground fault or varistor
defective
C Yellow LED: Disturbance