parallel operation, then opening breaker, unloading and stop automatically. All the
gen-sets are repeatedly started and stopped according to their total run time.
below module pre-set shutdown minimum percentage, the module with lowest priority
enters stop delay and then cools down and stops. If load exceeds the preset start
maximum percentage, the generators that are at rest will all start again.
3)
Balanced engine running time: Engine with the lowest total run time starts first. When
the running gen-set total run time exceeds the other genset balanced running time,
then the genset with the next lowest total run time starts (both “start on-load demand”
or “start all sets initially” modes are possible); other gensets after synchronization and