5.2.4 Battery
The battery test is for controlling the battery capacity to supply energy. The battery test can
either be made manually or automatically.
5.2.4.1 Battery test information
This menu provides information to show:
- the result of the latest battery test (OK, failed or aborted),
- date and time of the latest battery test,
- date and time of the next battery test. If the test is not scheduled, "----" is
displayed instead of the date.
5.2.4.2 Test programming
The battery test can be made automatic from the control panel by setting the
frequency, the day of the week and the time.
BATTERY: BATTERY TEST PROGRAMMING
BATTERY TEST: inactive
PROGRAMMED ON: Friday at 20:00
EVERY: 8 weeks
5.2.4.3 Battery measurements
The following measurements can be displayed:
- Battery voltage,
- Battery current (minus sign in front of the value means the battery is
discharging)
- Battery temperature,
- Load rate.
BATTERY MEASUREMENTS
Vdc = 450 V I batt = - 56 A
Load rate :