37
locking nut and are inserted into the corresponding plastic shell
respectively until a clicking sound is heard, indicating that the
metal core is clamped into place. Tighten the locking nut.
Figure. 4-10 Assembly diagram of battery DC terminal connector
To remove the BAT positive and negative connectors from the battery
module or battery power distribution unit, insert the BAT positive and
negative connectors into the bayonet as shown in figure 4-11 and press
them down to remove the DC connectors, as shown in Figure 4-11.
Figure. 4-11 Disconnect PV connectors
5) Use a multi meter to check the positive and negative
poles ,Connect the assembled DC terminal connector to the DC
B+/B- input terminal on the battery power distribution unit, and
connect the other end to the inverter side. Ensure that the
connection is secure.