BTS E5~20-DS5 user manualV1.1
Copyright © Shenzhen SOFARSOLAR Co., Ltd
43
5. Commissioning
5.1. Double Check
Please double check the following items before running
Battery module, BDU and the base should be completely fixed.
Each BAT+/BAT- line is firmly connected, the polarity is correct, and
the voltage is in line with the accessible range.
The DC switch of the BDU is OFF, and the black start indicator is
OFF.
Ensure that the communication cable is firmly connected to the
terminal resistor.
Install sealing plugs on unused terminals or interfaces.
Cable is arranged reasonably, and the cable is tidy and without
damage.
5.2. Electrify for the First TimeImportant
1) Set the DC switch of the BDU to ON.
2) Press the black start switch on the BDU to power on the battery for
the first time. Observe the LED indicator on the BDU to check the
running status.
5.3.
Battery Parameter Settings
If the system uses SOFARSOLAR HYD series inverter, the battery
parameters can be set as follows:
Procedure
Battery Parameter Settings

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sofar solar BTS Series and is the answer not in the manual?

Sofar solar BTS Series Specifications

General IconGeneral
BrandSofar solar
ModelBTS Series
CategoryBattery Pack
LanguageEnglish

Related product manuals