5 — Specifications and Requirements
11
11042437_A
LED202 In-Ceiling Lighting System Operator Manual
5.4 Installation Requirements
Pre-Installation Verification
NOTE: For maximum flexibility in future lighting requirements, the building should be designed to
accommodate the maximum weight and power requirements for anticipated ceiling-supported
products.
Study the equipment manual and the equipment drawings to learn the configuration of the system to be installed.
Complete the checklist below. Completing the checklist will aid the installer in understanding these instructions.
• Verify ceiling support. Use the information given in the equipment drawings to verify enough ceiling support has
been provided to accommodate 26 lbs (11.8 kg) for each lighthead assembly.
• Verify that the correct ceiling support method has been determined and that the correct support materials have
been obtained.
• Verify the correct location for the lighthead(s) in the room.
• Consult the equipment drawings for layout information.
• Ensure electrical service for each lighting system installation is complete (including lockout, junction box, conduit,
fittings, and lighthead power cable) and capable of being locked out. These items are not furnished (except
junction box) or installed by STERIS.
Equipment Required
Item
Single Install Quantity Dual Install Quantity
• LED202 Light
1 2
• Electric Cable
100 ft 100 ft
• Wall Control
1 1
• Mounting Plate
1 1
• Chain Package (if applicable)
1 2
• ³⁄₈” Eyebolts
4 8
• Lock Washers
4 8
• Nuts
8 16
• Flat Washers
4 8
• Chains
4 8
• ⁵⁄₁₆” Turnbuckles
4 8
• Quicklinks 4 8
• Splice Connectors
3 6