• Nail the double joists in place with two 16 penny vinyl-coated sinker nails per joist hanger.
• In order to support the ceiling light, we will install a 2 by 4 support. Measure the distance
between the double joists and cut a 2 by 4 to this length. Nail the 2 by 4 between the double
joists centered from front to back of the cooler.
EXTERIOR SHEATHING
Before installing the door and in order to provide structural rigidity to your cooler we recommend
sheathing the outside of the cooler.
The outside sheathing also creates an air gap between the insulation, effectively increasing the overall
R-factor of your cooler walls.
A. FOR INDOOR COOLERS (ECO-COOLER)
Cut and fit 4’x 8’ - 7/16” OSB boards as necessary depending on the wall (cutting around A/C and door
openings) and screw (or nail) them to the walls at the top, bottom and along the studs every 9 - 12
inches.