73
Step 5 When the country is set to Australia, additionally set the applicable network service provider
and then the grid type.Tap Power Company to select the correct power company.
figure 7-5 Initialization Power Company
The image shown here is for reference only. Refer to the actual interface for the supported
network service providers.
table 7-1 Power Company Information
Network Service Provider
Grid Type
AS/NZS 4777.2:2015 /
AS/NZS 4777.2:2020 Australia A /
AS/NZS 4777.2:2020 Australia B /
AS/NZS 4777.2:2020 Australia C /
ENERGEX & Ergon Energy
• STNW1170: single phase < 10 kVA &
three phase < 30 kVA
• STNW1174 :30 kVA < PN ≤ 1500 kVA
Endeavour Energy MDI 0043
Ausgrid NS194
Jemena
• ≤ 10kVA per phase (or 30 kVA per three
phase)
• ELE GU 0014: 30-200kVA
CitiPower & Powercor
• ≤ 5 kVA for single-phase & 30 kVA for
three-phase
• > 30 kVA three-phase
United Energy
• UE-ST-2008.1: ≤ 10 kW for single-
phase & 30 kW for three-phase
• UE-ST-2008.2: > 30 kVA three-phase
PowerWater Embedded Generation Notice Photovoltaic
Systems:2020
User Manual 7 iSolarCloud App