EasyManuals Logo

Sungrow SG50CX Quick Guide

Sungrow SG50CX
21 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #2 background imageLoading...
Page #2 background image
TD_20210219_SG30-50-110CX Commissioning Guide_V1.1 Page 2 of 21
© SUNGROW AUSTRALIA GROUP PTY LTD All rights reserved.
As we continuously improving our products, changes to this document may occur without notice.
Contents
1 Introduction ......................................................................................................... 3
2 RS485 Connections ............................................................................................ 5
2.1 Inverter Connection (Daisy Chain) ................................................................ 5
2.2 Energy Meter Connection ............................................................................. 6
2.3 Connection to Logger1000 ............................................................................... 8
2.4 Connection via EyeM4 ...................................................................................... 9
3 Web Portal Setup ...............................................................................................11
3.1 Access Web Portal .......................................................................................11
3.2 Set local time ................................................................................................12
3.3 Scan for Inverters .........................................................................................13
3.4 Add Energy Meter ........................................................................................14
3.5 Enable Remote Control ................................................................................16
3.6 Internet Connection ......................................................................................17
3.6.1 Connect via Ethernet Cable (Logger1000 only) ........................................17
3.6.2 Connect via WiFi (Logger1000 and EyeM4C) ...........................................17
3.6.3 Connect via 4G (EyeM4A Only) ................................................................18
3.7 Add CT Transformation Ratio.......................................................................19
3.8 Setup Export Control if required ...................................................................19
4 Create Plant on iSolarCloud ...............................................................................20
5 Updating the Logger1000/EyeM4.......................................................................21

Other manuals for Sungrow SG50CX

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Sungrow SG50CX and is the answer not in the manual?

Sungrow SG50CX Specifications

General IconGeneral
Max. DC Voltage1100 V
MPPT Voltage Range200 V - 1000 V
Max. Input Current per MPPT26 A
Number of MPPTs4
Rated AC Output Power50 kW
Max. AC Output Current76 A
Frequency50 Hz / 60 Hz
Efficiency98.6%
Start Voltage200 V
Number of DC Inputs per MPPT2
Max. AC Apparent Power55 kVA
AC Voltage Range310 V - 480 V
Power Factor at Rated Power1
Adjustable Power Factor Range0.8 leading - 0.8 lagging
THDi< 3%
DC SwitchYes
AC Surge ProtectionType II
DC Surge ProtectionType II
Protection ClassI
Cooling MethodSmart forced air cooling
Protection DegreeIP66
Protection LevelIP66
Operating Temperature Range-25°C to +60°C
Humidity0-100%
AC Output Voltage3 / N / PE, 220 V / 380 V, 230 V / 400 V