EcoInsight I, O & M Guide
Telkonet, Inc.
For Use with Firmware Version 2.x
20800 Swenson Drive, Suite 175
High Voltage Installation
Waukesha, WI 53186
Revision 4.2
(414) 302-2299
Page 7 www.telkonet.com
CAUTION!
Weco terminal on-site wiring for high voltage installation is not allowed. You must use
the pre-shipped 16-guage wired backplate provided by Telkonet.
High voltage installation should only be performed by a qualified heating & air
conditioning contractor or licensed electrician.
Failure to understand and follow all instructions carefully before installing or
operating this device could cause personal injury and/or property damage.
All wiring must conform to local and national electrical ordinances and codes.
Prevent electrical shock, personal injury, and equipment damage: prior to installation
or service, disconnect system’s electric power at main fuse or circuit breaker box.
High Voltage Installation
(For Low Voltage Installation instructions, see page 14.)
Mounting Preparation
Back plate type must be defined as low or high voltage prior to shipment.
For all high voltage installations a single gang mud ring must be mounted VERTICALLY on a JBOX. A Telkonet
JBOX Adapter Plate is required for all JBOX installations.
Required Equipment
High Voltage Backplate
Telkonet High Voltage JBOX Adapter Plate
EcoInsight (P/N: SS6000)
Two #6-32 1” screws
Four #5 ½” coarse thread screws
Voltmeter
Level
Phillips screwdriver
UL rated insulating tape
Wire stripper
Wire nuts
Pigtail SS6000/SS6500 for J5
Pigtail SS6000/SS6500/ SS6550
for J8
EcoInsight Installation