EcoInsight I, O & M Guide
Telkonet, Inc.
For Use with Firmware Version 2.x
20800 Swenson Drive, Suite 175
Low Voltage Installation
Waukesha, WI 53186
Revision 4.2
(414) 302-2299
Page 14 www.telkonet.com
Low Voltage Installation
Always ensure power has been turned off before starting installation.
Required Equipment
EcoInsight (P/N: SS6000)
Voltmeter
Level
Phillips Head Screwdriver
Precision Screwdriver
UL rated insulating tape
Wire stripper
Wire nuts
Additional Hardware Required for Drywall Mount
4 – 50 lb. EZ-Lock anchors and provided screws
Additional Hardware Required for VERTICAL JBOX Mount
Telkonet JBOX Adapter Plate
Two #6-32 1” screws
Four #5 ½” coarse thread screws
Additional Hardware Required for HORIZONTAL JBOX Mount
Two #6-32 1” screws
1 Speed Nut (flat-type speed nut fastener that accommodates a #6-32 1” screw as shown in Figure
12.
Figure 12: Speed Nut
EcoInsight Installation
Step 1 If applicable, determine the location in the room where the thermostat will be installed.
(See Thermostat Location Planning section, page 4.)
Step 2 Turn off power at EcoInsight mounting location using a disconnect switch or breaker
lockout/tag out on appropriate breaker panel.
Step 3 Test that power is off by using a voltmeter.