APPENDIX “A”
SVF036.DOC 04/12/13 REV 1 THOMSON TECHNOLOGY
©
9087A - 198
th
Street, Langley, B.C. Canada V1M 3B1 Telephone (604) 888-0110 Telefax (604) 888-3370
position for the 3-second neutral delay period, then the mechanism will complete the transfer and close the Utility power
switching device to return the load to the Utility source. Once the load has transferred onto the utility source, the engine
will continue to run for the 2-minute cool down time delay period and will then it will automatically stop.
19) Perform a power outage test by opening the upstream utility feeder breaker. The TSC 800 controller display will go blank;
the generator set will start after the 3-second engine start delay has expired. The generator should transfer on load as
described in item #17 above.
20) Return the transfer switch to utility power by re-closing the upstream utility breaker. The load should re-transfer back to
the utility supply and the engine should stop as described in item #19 above.
21) Repeat tests #17 through #21 two (or more) times to ensure correct operation.
22) On completion of commissioning ensure all controls are left in automatic.
23) If required, forward document or drawing updates to Thomson Technology if revisions are required and provide the end
user with a set of marked-ups to be retained on site.
24) Ensure copies of manuals for the equipment are on site.
25) Record and forward list of deficiencies to the appropriate parties where applicable.