98
CVHE-SVX005B-EN
Appendix A: Forms and Check Sheets
The following forms and check sheets are included for
use with Trane start-up of CVHE, CVHF, and CVHG
CenTraVac chillers. Forms and check sheets are used,
as appropriate, for installation completion verification
before Trane start-up is scheduled, and for reference
during the Trane start-up.
Where the form or check sheet also exists outside of
this publication as standalone literature, the literature
order number is also listed.
CTV Form Installation Completion and Request
for Trane Service (CTV-ADF001*-EN)
CenTraVac Chiller Start-up Tasks to be Performed
by Trane
CenTraVac Chiller Annual Inspection List
CenTraVac Operator Log
Unit Start-up/Commissioning
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.