98
CVHE-SVX005B-EN
Appendix A: Forms and Check Sheets
The following forms and check sheets are included for
use with Trane start-up of CVHE, CVHF, and CVHG
CenTraVac™ chillers. Forms and check sheets are used,
as appropriate, for installation completion verification
before Trane start-up is scheduled, and for reference
during the Trane start-up.
Where the form or check sheet also exists outside of
this publication as standalone literature, the literature
order number is also listed.
• CTV Form — Installation Completion and Request
for Trane Service (CTV-ADF001*-EN)
• CenTraVac Chiller Start-up Tasks to be Performed
by Trane
• CenTraVac Chiller Annual Inspection List
• CenTraVac Operator Log
Unit Start-up/Commissioning
IImmppoorrttaanntt:: Start-up must be performed by Trane or an
agent of Trane specifically authorized to
perform start-up and warranty of Trane
®
products. Contractor shall provide Trane
(or an agent of Trane specifically
authorized to perform start-up) with notice
of the scheduled start-up at least two weeks
prior to the scheduled start-up.