26 RT-SVX058D-EN
Start Up
Standard Economizer Start-Up
1. Set the minimum position setpoint for the economizer
to the required percentage of minimum ventilation
using the setpoint potentiometer located on the
Economizer Control (ECA).
The economizer will drive to its minimum position
setpo
int,
exhaust fans (if applicable) may start at
random, and the supply fan will start when the
SERVICE TEST is initiated.
The Exhaust Fan will start anytime the economizer
da
mper po
sition is equal to or greater than the exhaust
fan setpoint.
2. Verify that the dampers
stroked to the minimum
positi
on.
3. Verify that the dampers stroked to the full open
position
.
4. To stop the SERVICE TEST, turn the
main power
disconnect switch to the “Off” positi
on or proceed to
the next component start-up procedure. Remove
electro mechanical test mode connections (if
applicable).
LLE Controls Test Procedure
See unit schematic for correct wire numbers.
Use the CHECKOUT menu in the Installation Instructions
to test the damper operation and any co
nfigured outputs.
Only items that are configured are shown in the Checkout
menu.
To Perform Checkout Tests:
1. Scroll to the desired test in the checkout menu using
the
and buttons.
2. Press the
button to select the item.
3. “RUN?” is displayed.
4. Press
to start the test.
5. The unit pauses and then displays “IN PROGRESS”.
6. When the test is complete, “DONE” appears.
7. When all parameters have been tested, press
(Menu Up) to end the test (e.g. turn off the relay).
No
tes:
• The checkout tests can all be performed at the time of
installation or any time during the operation of the
system.
• JADE will be in "set up" mode for the first 60 minutes
after powered. If OA sensor or Sylk Bus device (sensor
or actuator) is disconnected during the set up mode,
the JADE will not alarm that failure. The MA sensor is
a system "critical" sensor, if the MA sensor is removed
during the set up mode, the JADE will alarm. After 60
minutes the JADE controller will change to operation
mode and all components removed or failed will alarm
in the operation mode.
• Up
on power up (or after a power outage or brownout),
the JADE controller m
odule begins a 5 minute power
up delay before enabling mechanical cooling.
Compressor Start-Up
1. Attach a set of service gauges onto the suction and
discharge gauge ports for each circuit. Refer to the
refrigerant circuit illustration in the Service Facts.
Using the Service Test Guide, per
form th
e proper test
mode connections.
Scroll Compressors
a. Once the compressor has started, verify
that the
rotation is correct. If wired correctly the suction
pressure should drop and the discharge pressure
should rise. If a scroll compressor is rotating
backwards, it will not pump and a loud rattling
sound can be observed.
b. If the electrical phasing is correct, before
co
ndemning a compressor, interchange any two
leads (at the compressor Terminal block) to check
the internal phasing. Refer to the following
illustration for the compressor terminal/phase
identification. Do not allow the compressor to
operate backwards for more than 5 seconds.
Operation for a period of time longer than this will
result in compressor damage. Copeland (Alliance)
will experience failure also. If the compressor runs
backward for an extended period, the motor
winding can overheat and cause the motor winding
thermostat to open.
Note: Th
e Copeland SXA scroll compressors for R-4
10A
units use Trane OIL00094. Compressor types are
listed in Table 7, p. 26. The appropriate oil charge is
listed in Table 8, p. 26.
Table 7. Compressor types
Tonnage C1
GB*036 SXA031
GB*048 SXA042
GB*060 SXA051
Table 8. POE Oil recharge amount (fl. oz.)
Model C1
GB*036 21
GB*048 38
GB*060 38
2. After the compressor and condenser fan have started
and operated for approximately 30 minutes, observe
the operating pressures. Compare the operating