Horizontal Discharge Conversion WSC036A-WSC060A, WSC036E, WSC048E
Supplies Needed by Installer for Conversion: 3 oz. tube of High Temperature RTV sealant.
(500°F/260°C: Similar to Dow Corning 736)
Note: Failure to use recommended sealant could result in unit performance loss.
If a unit is to be converted to a Horizontal discharge, the following conversion must be performed:
1. Remove RETURN and SUPPLY duct covers.
2. Locate supply cover. Apply ¼ in. (6mm.) continuous bead of 500°F RTV sealant to the flange as
shown.
3. Position SUPPLY DUCT COVER as shown, rotate 90 degrees to allow entrance into supply
opening.
Note: If unit is equipped with Discharge Air Sensing option refer to the following figure for proper
tube positioning based on unit tonnage.
4. Slide SUPPLY DUCT COVER into duct openings until inward edge of duct cover engages with
the 2 retaining clips on the duct flanges. Secure the outward edge of each duct cover with 2
screws.