Version 1.7 (June 2017)
TSI Flowmeters Ltd.
11
4.3 STATIC PRESSURE MEASUREMENT
1) Attach Flowmaster to standpipe.
2) Attach ball valve to exhaust side of Flowmaster. 
Ensure ball valve is partially open.
3) Crack open the hydrant slowly. All air will be 
expelled from the standpipe when water begins to 
drain from the ball valve. Close the ball valve.
5) When reading is taken, close hydrant fully.
4) Read static pressure (in bar).
6) Open the ball valve to exhaust pressure from the 
meter and standpipe. Remove the blanking plug and 
progress to ow test.
4.4
FLUSHING
1) Equipment required for ushing
2) Flowmaster connected to standpipe (through 
hose length)
3) Adjust valve position to achieve desired ow rate
4) Record volume discharged for inclusion in 
leakage gures