17 Before Leaving Jobsite
Before leaving jobsite:
Installed ASSE 1017 or 1070 tempering valve
Installed wall retaining clips (bottom)
Flushed heating system
Boiler and system filled with water
Air purged from boiler system
No loose, uninsulated or miswired connections
Checked for gas leaks
Checked gas inlet pressure
Performed combustion test
 Screw cap in vent adapter
No errors or holds present on display
Tested additional field installed controls for functionality outlined by manufacturer (i.e. LWCO, high
limit, or other controls)
Set proper CH temperature set point
Set proper DHW temperature set point
Tested DHW operation to confirm tempering valve setting
Verify system pump operation
Adjusted heating thermostat to its final set point
 Checked all valve and control settings
Reviewed User’s Information Manual and system operation with owner/operator