REQUIRED WATER FLOW ALARM TEST
Perform the water flow alarm test on a frequency required by the
current NFPA-25 code or LPCB/EN guidelines. The authority having
jurisdiction in the area may require these tests on a more frequent
basis. Verify these requirements by contacting the authority having
jurisdiction in the affected area.
1. Notify the authority having jurisdiction, remote station alarm
monitors, and those in the affected area that the water flow alarm
test will be performed.
CAUTION
Use caution to prevent opening the system main drain valve
accidentally.
Opening the system main drain valve will cause the valve to
operate.
Failure to pipe the system main drain valve to a proper wastewater
drain will result in property damage.
2. Open the water supply main drain valve fully to flush the water
supply of any contaminants.
3. Close the water supply main drain valve.
4. Open the alarm test ball valve. Confirm that mechanical and
electrical alarms are activated and that remote monitoring stations,
if provided, receive an alarm signal.
5. Close the alarm test ball valve after verifying proper operation of all
alarms.
6. Push in the ball drip plunger on the alarm manifold assembly to
verify that there is no pressure in the alarm line.
7. Verify that all alarms stopped sounding, that the alarm line drained
properly, and that remote station alarms reset properly.
8. Confirm that the ball drip on the alarm manifold assembly is not
leaking water or air.
9. Notify the authority having jurisdiction, remote station alarm
monitors, and those in the affected area that the valve is back in
service. Provide test results to the authority having jurisdiction, if
required.
Ball Drip
Plunger
(Steps 6 & 8)
Water Supply
Main Drain
Valve
(Steps 2 & 3)
Alarm Test
Ball Valve
(Steps 4 & 5)
I-769N.Preaction/AC-ELEC_22 REV_A

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Victaulic 769N FireLock NXT Series and is the answer not in the manual?

Victaulic 769N FireLock NXT Series Specifications

General IconGeneral
BrandVictaulic
Model769N FireLock NXT Series
CategoryControl Unit
LanguageEnglish

Related product manuals