Checking the diaphragm expansion vessel and system pres-
sure
1. Pull the leads from air pressure
switch A.
2. Secure cover B.
3. Check the diaphragm expansion
vessel inlet pressure at test port C
and recharge, if required.
4. Secure lid B and push the leads
onto air pressure switch A.
Checking all gas equipment for soundness at operating pres-
sure
Danger
Escaping gas leads to a risk of
explosions.
Check gas equipment for
soundness.
Further details regarding the individual steps (cont.)
36
Commissioning, inspection, maintenance
5862 831 GB