Place a large bucket beneath discharge tee outlet. Start
motor. If pump is offset from well 4 feet or more, it may
take a few minutes for pump to prime. Failure to prime
in 5 minutes: Stop motor, remove 1-1/2" plug from
discharge tee, add more water, try again.
STEP
11
Allow pump to run long enough to clear well of sediment
and to ensure well will not run dry. Stop motor. Thread
1-1/2" male PVC adapter into discharge tee outlet.
STEP
12
1-1/2" MALE
PVC ADAPTER
Cement as many PVC pipe sections and couplings as
needed to connect the 1-1/2" male PVC adapter to
inground sprinkler system. Complete installation should
look like illustration.
STEP
13
COMPLETE
CASED WELL
INSTALLATION