Page 9 of 40 Webasto Charging Systems, Inc.
Intelligent Fast-Charging System GSE Installation Guide for the DVS300/330/400 and MVS330/400
31504-76-0101
IMPROPER INSTALLATION CAN CAUSE FIRE
WARNING
• Do not install or place the unit on, over, or near combustible surfaces.
• Do not install the unit near ammable items.
• Do not block the air intake to, or exhaust from, the unit.
• Do not block airow to the unit.
• Replace blown fuses only with the same type and rating of fuse.
• Do not overload the building wiring: be sure that the utility power service is
properly sized, rated, and protected to handle this unit. Use the unit only with the
circuits provided, with the minimum wire size specied in the installation section.
• Protective bollards should be installed where the GSE location is subject to
damage from vehicle activity.
• Do not install the power station if there is physical damage to the power station,
coupler, or cable.
• Do not subject the cable or coupler to damage or stress. Do not step on the
coupler cable.
• Do not hang the power station from the coupler cable.
• Do not disassemble the DVS or power station.
• Use the metal conduit only above ground.
• Follow the National Electrical Code (NEC) and local codes, both of which take
precedence. If any instructions in this guide conict with NEC or local codes,
then contact WCSI for further information.
CAUTION
ELECTROSTATIC DISCHARGE PRECAUTIONS
Electronic circuits are sensitive to damage from electrostatic discharge (ESD).
Persons servicing this equipment should be trained in proper techniques for avoiding
ESD damage to electronic circuits.
• Wear an appropriate ESD wrist strap connected to the equipment chassis,
as a minimum, when handling circuit boards.