4 Safety instructions
1 Always ensure that the main water tap in the supply line is closed when the machine is
switched off and that the main power switch outside the machine is off or the mains plug is
disconnected from the socket as there is a risk of water escaping from the machine.
2 The installed component approved safety equipment prevents an impermissibly high pressure
or temperature increase in the hot water boiler. If the safety valve is actuated one-time then
the machine must be switched off at the local main switch and the main stop cock on the
drinking water supply line closed. Switch off the machine if any faults arise on the hot water
boiler. Inform the WMF customer service team and do not switch on the machine again
before the fault has been removed.
3 Do not use the machine in the open air. The water system must be emptied if there is frost.
4 The device must not be sprayed with a water hose. Use of steam cleaning, steam jet devices
and similar equipment for cleaning purposes is not permitted. Clean the surface of the coffee
machine using a soft cloth or by using products from our WMF care range.
5 The device must be set on a flat, level and secure surface.
6 Do not let children near the machine!
7 Do not use the machine if it does not work properly or if has been damaged
Shutting down the machine – company holidays
1 If the machine is to be shut down for an extended period, a general cleaning should be carried
out first and the grouts collector should be emptied. Drain the machine first to prevent frost
damage if there is any risk of freezing. A WMF Customer Service Technician must be called
promptly in such cases.
2 After several weeks of shutdown for holidays, we recommend that the full automatic cleaning
program be run at least twice before the machine is started up again.
Regulations
Refer to rating plate for boiler data.
The hot water boiler complies with the Pressure Equipment Directive 97/23/EC, Category 1,
Module A.
The hot water boiler is subject to neither notification nor licensing. Each hot water boiler is
subjected to hydrostatic tests before delivery to the customer.
The operator of such plants must ensure that the safety devices are carely serviced and inspected.