YASKAWA ELECTRIC TOBP C730600 95A U1000-Series Option PS-U10 Installation Manual 41
6 Verifying Operation
6 Verifying Operation
After correctly wiring and installing the option, use the procedure below to make sure that
the option operates correctly:
1.
Energize the drive and make sure that 24 Vdc external power is supplied to the 24 V
connector plug, and the 24 V connector plug is connected to the option.
2.
De-energize the drive. The 24 V external power supply should provide power to the
drive control unit.
3.
The red LED on the option identifies when the option is operating correctly.
4.
The digital operator on the drive will flash “Fdv” or “AUv” for approximately 10
seconds to show an undervoltage condition on the drive.
If “Fdv” or “AUv” does not flash on the display screen, make sure that the wiring is
correct.
If “Fdv” or “AUv” does not flash on the keypad after making sure that the wiring is
correct, the drive or option may be damaged.
Power Supply and the Control Circuit
Table 3 outlines the conditions under which the option provides power to the control circuit.
Table 3 Power Supply and Control Circuit
Drive Main Circuit Input
Power Supply
Power from Option
Control Circuit
Operation in Drive
Drive Operation
ON ON
Normal operation
Possible
ON OFF Possible
OFF ON Not possible
OFF OFF Stop Not possible
TOBP_C730600_95A_2_0_E.fm 41 ページ 2023年2月13日 月曜日 午後1時8分