9. If the input power cable has a shield, twist it into a bundle, mark it with
yellow-green and connect it to the PE terminal.
10. Mark the second grounding connector of the input side with the yellow-green
and connect it to the PE terminal. (Second PE conductor is required by the
drive safety standards IEC61800-5 and UL 61800-5.)
11. Connect the phase conductors of the input power cable to the L1, L2 and L3
input terminals.
12. Mechanically attach the cables on the outside of the drive.
Connecting the control cables
Refer to Default I/O connection diagram (ABB standard macro) for the default I/O
connections of the ABB standard macro. For other macros, refer to the
ACS180
firmware manual
(3AXD50000467860 [English]).
68 Electrical installation