2 Installation and Commissioning
2.1 Installation
1. Fix the unit vertically to the wall and secure using suitable
fixings.
2. Avoid tension of the housing.
Fig. 2.1 Dimensions
459 (18.07)
380 (14.96)
424 (16.7) Fixing Centers
266 (10.47) Fixing Centers
280 (11.02)
Note. The unit doors swing to the left when opened. Allow
sufficient space for the doors to open when preparing for
installation.