7 Installation planning
Clearances needed to allow proper airflow on the UPS system and to allow door opening.
Figure 2: Top view and indication of the minimum clearances for UPS + other cabinets in row.
Table 3: minimum clearances for UPS + other cabinets in row.
PowerWave 33 Series 3 Cabinets 60 / 80 / 100 / 120
UPS + battery cabinets in
row.
A
Back clearance for ventilation
(forced air outlet)
0 mm 100mm
4)
B
Front clearance needed to allow a
correct door opening
1000 mm
C
Maximum door opening angle 115°
D
Top Clearance
(Top clearance is only needed if
there is no side clearance)
400 mm
4)
Battery cabinet requires 100mm clearance for natural ventilation. The UPS does not require any back clearance.
Accessibility
Totally front accessible for start-up and maintenance
Positioning
Strictly indoor in a temperature and humidity controlled environment. The
UPS can be placed against the wall (back side)
Power and signals wiring Front bottom