5. Measure that the installation is de-energized.
• Before and after measuring the installation, verify the operation of the voltage tester
on a known voltage source.
• Make sure that the voltage between the drive input power terminals (L1, L2, L3)
and the grounding (PE) busbar is zero.
• Make sure that the voltage between the drive output terminals (T1/U, T2/V, T3/W)
and the grounding (PE) busbar is zero.
6. Install temporary grounding as required by the local regulations.
7. Ask the person in control of the electrical installation work for a permit to work.
Safety instructions 11