5. Measure that the installation is de-energized.
Before and after measuring the installation, verify the operation of the voltage tester
on a known voltage source.
Make sure that the voltage between the drive input power terminals (L1, L2, L3)
and the grounding (PE) busbar is zero.
Make sure that the voltage between the drive output terminals (T1/U, T2/V, T3/W)
and the grounding (PE) busbar is zero.
6. Install temporary grounding as required by the local regulations.
7. Ask the person in control of the electrical installation work for a permit to work.