Start-up and acceptance test
Contents of this chapter
This chapter describes the start-up, acceptance test procedure, and validation of the safety
function.
Validation of the safety functions
You must do an acceptance test (validation) to validate the correct operation of safety
functions.
Competence
The person who does the acceptance test of the safety function must be a competent person
with expertise and knowledge of the safety function and functional safety, as required by
IEC 61508-1 clause 6. This person must document and sign the test procedures and report.
Validation procedure
You must do the acceptance test using the checklist given in this manual:
at the initial start-up of the safety function
after changes related to the safety function (wiring, components, safety function -related
parameter settings, etc.)
after maintenance work related to the safety function.
The acceptance test must include at least the following steps:
you must have an acceptance test plan
you must test all commissioned functions for proper operation, from each operation
location
you must document all acceptance tests
you must sign and store the acceptance test report for further reference.