• The chapter Verifying settings by secondary injection contains instructions on
how to verify that each included function operates correctly according to the
set values.
• The chapter
Commissioning and maintenance of the fault clearing system
discusses maintenance tests and other periodic maintenance measures.
• The chapter Fault tracing and repair explains how to troubleshoot.
• The chapter
Glossary is a list of terms, acronyms and abbreviations used in
ABB technical documentation.
1.1.3 Intended audience
General
The installation and commissioning manual addresses the personnel responsible for
the installation, commissioning, maintenance and taking the protection in and out
of normal service.
Requirements
The installation and commissioning personnel must have a basic knowledge in
handling electronic equipment. The commissioning and maintenance personnel
must be well experienced in using protection equipment, test equipment, protection
functions and the configured functional logics in the protection.
1.1.4 Related documents
Documents related to REG670
Identity number
Operator’s manual 1MRK 502 028-UEN
Installation and commissioning manual 1MRK 502 029-UEN
Technical reference manual 1MRK 502 027-UEN
Application manual 1MRK 502 030-UEN
Product guide customized 1MRK 502 031-BEN
Product guide pre-configured 1MRK 502 032-BEN
Rotor Earth Fault Protection with Injection Unit RXTTE4 and REG670 1MRG001910
Connection and Installation components 1MRK 513 003-BEN
Test system, COMBITEST 1MRK 512 001-BEN
Accessories for 670 series IEDs 1MRK 514 012-BEN
670 series SPA and signal list 1MRK 500 092-WEN
IEC 61850 Data objects list for 670 series 1MRK 500 091-WEN
Engineering manual 670 series 1MRK 511 240-UEN
Buyer’s guide REG 216 1MRB520004-BEN
Communication set-up for Relion 670 series 1MRK 505 260-UEN
1MRK 502 029-UEN A Section 1
Introduction
13
Installation and commissioning manual