ABB Relion 670 series - Local HMI Use and Operations; Logging On to the IED via Local HMI

ABB Relion 670 series
260 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
en07000141.vsd
Cc
Cc
1)
External
Equipment (PC)
PE 1) 3)
2)
PE
IED
X1
1 65432
IED
1 65432
X1
PE
PE
IEC07000141 V1 EN
Figure 52: Communication cable installation, 2-wire
Where:
1 The inner shields shall be connected together (with an isolated terminal block) and only
have one earthing point in the whole system, preferably at the external equipment (PC).
The outer shield shall be connected to Protective Earth (PE) in every cable end that is, to PE
at all IED terminals and to PE at External equipment (PC). The first IED will have only one
cable end but all others of course two.
2 Connect according to installation instructions for the actual equipment, observe the 120
ohms termination.
3 The protective earth should be close to the external equipment (< 2m)
Cc Communication cable
PE Protective earth screw
1MRK 502 029-UEN A Section 5
Installing the IED
79
Installation and commissioning manual