-2U
0
Operate area
2I
0
RCADir = 0º
ROADir = 80º
IEC15000257-1-en.vsdx
IEC15000257 V1 EN-US
Figure 26: Example characteristic
Non-directional earth fault current protection
SEMOD175060-117 v10
Procedure
1. Measure that the operate current is equal to the INNonDir> setting.
The function activates the START and STDIRIN output.
2. Measure the operate time of the timer by injecting a current of 200% of the
operate value.
3. Compare the result with the expected value.
The expected value depends on whether definite or inverse time was selected.
4. Continue to test another function or complete the test by setting the test mode
to Off.
Residual overvoltage release and protection
SEMOD175060-131 v6
Procedure
1. Measure that the operate voltage is equal to the UN> setting.
The function activates the START and STUN signals.
2. Measure the operate time by injecting a voltage 1.2 times set UN> operate
value.
3. Compare the result with the set tUN operate value.
4. Inject a voltage 0.8 · UNRel> and a current high enough to operate the
directional function at the chosen angle.
5. Increase the voltage until the directional function is released.
6. Compare the measured value with the set UNRel> operate value.
1MRK 506 377-UEN C Section 10